University of Alaska Fairbanks officials say the problems they’ve encountered in getting the $245 million power plant fully operational have pushed the project behind schedule and over budget. But they think they’ve finally worked out most of the bugs, and they’ve come up with a new estimate on when the plant will be online.


Tim Ellis/KUAC

The University of Alaska Fairbanks celebrated the completion of the campus’s $245 million power plant back in August, in anticipation the facility would be online by the end of the year. But UAF officials say a structural problem that was repaired last month and a faulty electrical component discovered last weekend will keep the plant from going online until spring.


KUAC file photo

Construction work on the University of Alaska Fairbanks’s new coal-fired powerplant is complete and workers are preparing for the first test of a major component by the end of the month. If all goes as planned, the $245-million plant should be fully operational around Thanksgiving.